Starbase activities (2024-08-21):
- Aug 20th cryo delivery tally.
- Continuous flight auger drill moves from pad B to Sanchez. (ViX, Golden 1, Golden 2, Golden 3)
- Pad A: Ship quick disconnect is extended. All 3 bumper blocks are removed from both starboard and port chopsticks. Chopstick movement observed in the evening. Newly installed "acuter" (actuator) piston is spotted by Gisler.
- Pad B: The 9th and final tower module is stacked. (LabPadre, ViX 1, ViX 2, NSF 1, NSF 2, NSF 3, NSF 4, NSF timelapse, NSF livestream, Golden, cnunez 1, cnunez 2, cnunez 3, Gisler 1 (pre-lift safety meeting), Gisler 2, Gisler 3, Gisler 4, Gomez 1, Gomez 2, clwphoto1, SpaceX)
- LR11000 crane is on the move.
- Massey's: The "can crusher" jig is placed on Test Tank 16. Horizontal tank 2 of 3 arrives from Brownsville port. (ViX, Gisler)
- Starkitty sighted :) (ViX 1, ViX 2)
Other:
- Compilation of Tower B stacking. (LabPadre)